It involved a major shut down of existing equipment alongside rerouting of pipework sections, whilst maintaining the services to hospital departments with temporary facilities.
The new 3 floor extension consisted of 11 wards and 3 specialist departments supplied with Oxygen, Medical Air 4 and Vacuum services fully meeting the HTM 02-01 standards.
Each ward / department had the full range of NIST line valves, Area Valve & Service Units, terminal units fitted and area alarm systems.
Pipework services were installed linking all areas, including a major oxygen main diversion section to the new VIE plant.
Fully tested and commissioned to the client’s representative’s approval.
Staff training was completed.